Arcadia's Capital Improvement & Equipment Replacement Plan FY2025-2030 programmes $24,079,700 across 32 projects — new buildings, repaved streets, replaced water mains. This is the part of a budget you can see out of a window, so it is shown on a map.

Read the shapes carefully

The city's plan describes where each project is in words — "City Hall", "Baldwin Ave from Camino Real Ave to Longden Ave", "Various Locations". It contains no coordinates at all. Every shape below was placed by One Public Budget by matching that text against public street and place data. The locations are our inference, not the city's data. Each one tells you how it was placed and how confident we are. Where we could not place a project, it is listed below the map rather than dropped or guessed at.

On the flat map, size is the place and shade is the money. Each site is drawn as the shape that is really there — the buildings, the park, the street — so a big shape is a big place, not a big number. How dark it is shaded is the site's combined cost. Where several projects landed at one place they are shown once, with the combined figure; the site's own page lists them separately.

15 projects with a location we could place

Shade — combined cost at the site

  • under $380,000 (4 sites)
  • $380,000 to $750,000 (4 sites)
  • $750,000 to $2,120,000 (2 sites)
  • $2,120,000 to $3,850,000 (0 sites)
  • $3,850,000 and over (2 sites)

Darker is more. The bands are quantiles — chosen so each holds roughly the same number of sites — not equal steps of money, which is why each one prints its own range. They are computed over every site in the whole plan, so a site keeps its shade when you change the year or the funding source.

Shape — what is there

  • The assessor's lot at that location
  • A street, where the plan names one
  • A dashed marker — nothing is mapped there
  • A lot outside Arcadia — our matching error

Size is the size of the place and means nothing about money. A dashed marker circle is the same size at every site and says only "somewhere here". Every outline is where One Public Budget believes the project is, matched from the words the plan prints — not a location the city published. The lot itself is a county record; which lot is our guess.

A hollow, finely dashed lot is one we placed outside Arcadia. Every project in this plan is Arcadia's, so those are our matching errors — the figure and the city's words are right, the position is not. They are drawn rather than hidden. Being inside the city is not proof of correctness either: a project can be matched to the wrong lot two streets away and nothing here will catch it.

A site's figure is the sum of the projects that landed there, which is arithmetic by One Public Budget — the city publishes a figure per project, not per place. Hover any site for that sum and the projects behind it, or open the site for the full breakdown.

Basemap: US Census Bureau TIGER/Line 2023 (public domain), © OpenStreetMap contributors (ODbL), and elevation from the USGS 3D Elevation Program (3DEP, public domain). Served from this site; no map tiles are fetched from anyone else.

Every site on the map

The same 12 places the map shades, as a table — so the combined figures the map shows exist in readable form and not only as colour. Sorted by combined cost, highest first.

Capital project sites with combined cost and the number of projects at each
Site Combined cost Projects Shading band
Orange Grove Park $6,000,000 1 band 5 of 5 ($3,850,000 and over)
Colorado Place $4,500,000 1 band 5 of 5 ($3,850,000 and over)
Santa Anita Avenue $1,350,000 1 band 3 of 5 ($750,000–$2,120,000)
Baldwin Ave $900,000 1 band 3 of 5 ($750,000–$2,120,000)
Arcadia Public Library $700,000 1 band 2 of 5 ($380,000–$750,000)
Duarte Park $600,000 1 band 2 of 5 ($380,000–$750,000)
Arcadia Wilderness Park $550,000 2 band 2 of 5 ($380,000–$750,000)
Arcadia Police Department $460,000 3 band 2 of 5 ($380,000–$750,000)
Los Angeles County Public Works $350,000 1 band 1 of 5 (under $380,000)
Fallen Leaf Road $100,000 1 band 1 of 5 (under $380,000)
Eisenhower Memorial Park $30,000 1 band 1 of 5 (under $380,000)
Arcadia High School $13,000 1 band 1 of 5 (under $380,000)
Total across these sites $15,553,000 15

Site totals are arithmetic by One Public Budget over the figures the plan printed per project. A project that covers several locations is counted in full at each of them, never divided between them, so this total can exceed the sum of those projects.

Every mapped project

The same 15 projects, as a table. Sorted by amount.

Capital projects placed on the map, with amount, location text, and how the location was determined
Project Amount Location, as the city wrote it How we placed it
Orange Grove Well Treatment - Design and Construction $6,000,000 Orange Grove Plant medium confidence matched to Orange Grove Park in OpenStreetMap
Colorado Place Complete Streets Extension Project $4,500,000 Colorado Place from Colorado Boulevard to Huntington Drive high confidence matched Colorado Place between its two named cross streets in the Census street network
Sewer Main Replacement Program $1,350,000 Santa Anita Avenue between El Dorado Street and Christina Street high confidence matched Santa Anita Avenue between its two named cross streets in the Census street network
Arterial Rehabilitation Program - Baldwin Ave from Camino Real Ave to Longden Ave $900,000 Baldwin Ave from Camino Real Ave to Longden Ave high confidence matched Baldwin Ave between its two named cross streets in the Census street network
Library Facility Improvements $700,000 Arcadia Public Library high confidence matched to Arcadia Public Library in OpenStreetMap
Encanto Park Stormwater Capture Project $600,000 Encanto Park in the City of Duarte medium confidence matched to Duarte Park in OpenStreetMap
Wilderness Park Debris Removal Design $450,000 Wilderness Park high confidence matched to Arcadia Wilderness Park in OpenStreetMap
Water Master Plan Update $350,000 Public Works Services Department medium confidence matched to Los Angeles County Public Works in OpenStreetMap
Police Department Facility Improvements $300,000 Police Department high confidence matched to Arcadia Police Department in OpenStreetMap
Upgrades to City Hall Green Room and Human Resources Offices $130,000 City Hall high confidence matched to Arcadia City Hall in OpenStreetMap
Stormdrain Repair Project $100,000 Fallen Leaf Road medium confidence matched the whole of Fallen Leaf Road in the Census street network; the form does not say which part
Wilderness Park Debris Wall Project $100,000 Wilderness Park high confidence matched to Arcadia Wilderness Park in OpenStreetMap
Eisenhower Park Basketball Court Resurfacing Project $30,000 Eisenhower Park high confidence matched to Eisenhower Memorial Park in OpenStreetMap
City Hall Facility Improvements $30,000 City Hall high confidence matched to Arcadia City Hall in OpenStreetMap
Arcadia High School Track Re-Striping $13,000 Arcadia High School high confidence matched to Arcadia High School in OpenStreetMap

9 projects the city describes as citywide

These are not missing from the map — they genuinely have no single place. Slurry sealing "various street locations", tree replacement "various locations". Putting a pin in the middle of town for these would invent a precision the city never claimed.

Citywide capital projects
ProjectAmountLocation, as the city wrote it
Pavement Rehabilitation Program $2,500,000 Various Street Locations within the City
Annual Slurry Seal Program $1,350,000 Various Street Locations Within the City
SCADA System Replacement $1,000,000 All Water Facilities and Sewer Lift Station within the City
Coordinated Integrated Monitoring Plan (CIMP) $263,000 Various Locations
Miscellaneous Traffic Signal Improvements $200,000 Various Locations
ADA Sidewalk and Ramp Improvements $200,000 Various Locations
Annual Tree Removal and Replacement Program $50,000 Various Locations
Fire Station Maintenance Program $25,000 All Fire Stations
Citywide Art Preservation $3,700 Various Locations throughout the City of Arcadia

8 projects we could not place

This is our shortfall, not the city's. These projects name a real place — a fire station, a water plant, a stretch of alley — that our matching could not pin down. They are listed here in full so that money is never quietly missing from the picture.

Capital projects One Public Budget could not place on the map
ProjectAmountLocation, as the city wrote it
Purchase and Install 800kw Generator at Live Oak Treatment Plant $850,000 Live Oak Water Treatment Facility
Fiber Network Extenson - Huntington Dr & Las Tunas Dr $500,000 Huntington Drive - 2nd Ave to 5th Ave & Las Tunas Dr - Baldwin Ave to El Monte Ave
Live Oak Avenue/Las Tunas Drive Corridor Traffic Signal Improvements $500,000 Las Tunas Drive Westerly City Limit to Live Oak Avenue Easterly City Limit
Fire Stations Facility Improvements $450,000 Fire Station 105, Fire Station 106, and Fire Station 107
Well Inspection and Rehabilitation Program $400,000 Orange Grove Well 6
Arterial Streets Miscellaneous Minor Repairs $125,000 S Baldwin Avenue near La Vida Lane
Veeder Root Project $100,000 Fire Station 105, Fire Station 107, Police Department, and PWSD Yard
Dana Gym Entrance Keypad $10,000 Dana Gym