Arterial Rehabilitation Program - Baldwin Ave from Camino Real Ave to Longden Ave
Previously Programmed Project · page 55 of the Capital Improvement & Equipment Replacement Plan FY2025-2030 · city contact: Kevin Merrill
$900,000
estimated total cost, as printed on the project form
Where the city says it is
Baldwin Ave from Camino Real Ave to Longden Ave
high confidence Located by One Public Budget, not by the city: matched Baldwin Ave between its two named cross streets in the Census street network. The plan itself contains no coordinates.
Five-year funding cycle
| Fiscal year | Funding source | Amount |
|---|---|---|
| FY 25-26 | Prop C | $900,000 |
| Total across the cycle | $900,000 | |
This total is the sum of the rows above, and it matches the estimated total the form prints. If those two had disagreed, this project would not be published at all.