Colorado Place Complete Streets Extension Project
New Project · page 49 of the Capital Improvement & Equipment Replacement Plan FY2025-2030 · city contact: Kevin Merrill
$4,500,000
estimated total cost, as printed on the project form
Where the city says it is
Colorado Place from Colorado Boulevard to Huntington Drive
high confidence Located by One Public Budget, not by the city: matched Colorado Place between its two named cross streets in the Census street network. The plan itself contains no coordinates.
Five-year funding cycle
| Fiscal year | Funding source | Amount |
|---|---|---|
| FY 25-26 | Other | $4,500,000 |
| Total across the cycle | $4,500,000 | |
This total is the sum of the rows above, and it matches the estimated total the form prints. If those two had disagreed, this project would not be published at all.