Dana Gym Entrance Keypad

New Project · page 67 of the Capital Improvement & Equipment Replacement Plan FY2025-2030 · city contact: Sara Somogyi

$10,000

estimated total cost, as printed on the project form

Where the city says it is

Dana Gym

none confidence One Public Budget could not match this description to a place it knows, so this project does not appear on the map. The description above is exactly what the city published.

Five-year funding cycle

Funding by year and source, exactly as the project form prints it
Fiscal yearFunding sourceAmount
FY 25-26 Capital Outlay $10,000
Total across the cycle $10,000

This total is the sum of the rows above, and it matches the estimated total the form prints. If those two had disagreed, this project would not be published at all.