Arterial Pavement Rehabilitation - First Avenue between Huntington Dr and Duarte Rd
Previously Programmed Project · page 143 of the Capital Improvement & Equipment Replacement Plan FY2025-2030 · city contact: Kevin Merrill
$1,300,000
estimated total cost, as printed on the project form
Where the city says it is
First Avenue between Huntington Drive and Duarte Road
high confidence Located by One Public Budget, not by the city: matched First Avenue between its two named cross streets in the Census street network. The plan itself contains no coordinates.
Five-year funding cycle
| Fiscal year | Funding source | Amount |
|---|---|---|
| FY 26-27 | Prop C | $1,300,000 |
| Total across the cycle | $1,300,000 | |
This total is the sum of the rows above, and it matches the estimated total the form prints. If those two had disagreed, this project would not be published at all.