Miscellaneous Traffic Signal Improvements
On-Going Project · page 137 of the Capital Improvement & Equipment Replacement Plan FY2025-2030 · city contact: Kevin Merrill
$700,000
estimated total cost, as printed on the project form
Where the city says it is
Various Locations
exact confidence The city describes this project as covering multiple locations, so One Public Budget does not place it anywhere specific. That is the city's own description, not a gap in our data.
Five-year funding cycle
| Fiscal year | Funding source | Amount |
|---|---|---|
| FY 26-27 | Measure M | $100,000 |
| Transportation Impact | $100,000 | |
| FY 27-28 | Measure M | $100,000 |
| Transportation Impact | $100,000 | |
| FY 28-29 | Measure M | $100,000 |
| Transportation Impact | $50,000 | |
| FY 29-30 | Measure M | $100,000 |
| Transportation Impact | $50,000 | |
| Total across the cycle | $700,000 | |
This total is the sum of the rows above, and it matches the estimated total the form prints. If those two had disagreed, this project would not be published at all.